Construction along 134th South
The Questar Gas Feeder Line is well underway and has now entered Herriman boundaries, as is painfully obvious for the residents of Herriman.
The length of the project is roughly an 8.5 mile stretch of 134th South spanning both Riverton and Herriman. Traffic control is in place in all work zones, with lane restrictions in place with at least one lane open in both directions. The speed limit in construction zones is 30 mph. Safety messages include driving cautiously, taking alternate routes when possible and obeying flaggers.
Questar will only work on one intersection at a time. They are nearing completion of their work at the 5000 W. intersection and will be moving on to NIGHT work only at the 5600 W. intersection within the next few weeks. The project through Herriman will extend to roughly 8000 West. Residents should expect probable lane restrictions and continually adjusting traffic patterns. The estimated project completion time is early April 2012
For questions, concerns or additional information, residents can call (801) 324-5548